UNDER CONSTRUCTION - Progress Report

 

ACTIVITY
ACTIVITY STATUS
VILLA A& B
VILLA C & D
VILLA L & M
VILLA N & O
1
Work in foundation & plinth
complete
complete
complete
complete
2
RCC Work
a
Ground floor columns
complete complete complete complete
b
Ground floor slab
complete complete complete complete
c
First floor columns
complete complete complete complete
d
First floor slab (roof)
complete complete complete complete
3
Masonary work
a
Ground floor masonary
complete complete complete complete
b
First floor masonary
complete complete complete complete
4
Gypsum plaster
a
Ground floor ceiling 
complete complete complete complete
b
First floor ceiling
complete complete complete complete
c
Ground floor walls 
complete complete complete complete
d
First floor walls
complete complete complete complete
5
External Plaster
complete complete complete complete
6
Plumbing
complete
complete
complete
7
Door frames & window fixing
complete complete complete complete
8
Balcony grill fixing
complete complete complete complete
9
Roof sheet
complete
complete
complete
complete
10
Tiling
a
Toilet & Kitchen
complete
complete
complete
complete
b
Sundeck
complete
complete
complete
complete
c
Rooms
complete
complete
complete
complete
11
Solar Water heating systems
complete
complete
complete
complete
12
Painting
a
Internal
complete
complete
complete
complete
b
External
complete
complete
complete
complete
APT E
APT F
VILLAS H,I
VILLAS J,K
1
Work in foundation & plinth
complete
complete
complete
complete
2
RCC Work
a
Lower ground floor columns
complete complete complete complete
b
Lower ground floor slab
complete complete complete complete
c
Ground floor columns
complete complete complete complete
d
Ground floor slab
complete complete complete complete
i
Second floor roof slab
complete complete N/A N/A
3
Masonary work
a
Lower ground floor 
complete complete complete complete
b
Ground floor 
complete complete complete complete
c
First floor 
complete complete complete complete
d
Second floor 
complete complete N/A N/A
4
Gypsum plaster
a
Ground floor ceiling 
complete complete complete complete
b
First floor ceiling
complete complete
complete
c
Ground floor walls 
complete complete complete complete
d
First floor walls
complete complete complete complete
e
Second floor walls
complete complete N/A N/A
f
Second floor ceiling
complete complete N/A N/A
5
External Plaster
complete complete complete complete
6
Plumbing
complete
complete
complete
7
Door frames & window fixing
complete complete complete complete
8
Balcony grill fixing
complete complete complete complete
9
Roof sheet
complete
complete
complete
complete
10
Tiling
a
Toilet & Kitchen
complete
complete
complete
complete
b
Sundeck
complete
complete
complete
complete
c
Rooms
complete
complete
complete
complete
11
Solar Water heating systems
complete
complete
complete
complete
12
Painting
a
Internal
complete
complete
complete
in progress
b
External
complete
complete
complete
complete
VILLA P&,Q
VILLA R &,S
VILLA Z &,Y
VILLA U &,T
1
Work in foundation & plinth
complete
complete
complete
complete
2
RCC Work
a
Ground floor columns
complete complete complete complete
b
Ground floor slab
complete complete complete complete
c
First floor columns
complete complete complete complete
d
First floor slab (roof)
complete complete complete complete
3
Masonary work
a
Ground floor masonary
complete complete complete complete
b
First floor masonary
complete complete complete complete
4
Gypsum plaster
a
Ground floor ceiling 
complete complete complete complete
b
First floor ceiling
complete complete complete complete
c
Ground floor walls 
complete complete complete complete
d
First floor walls
complete complete complete complete
5
External Plaster
complete complete complete complete
6
Plumbing
complete
complete
complete
complete
7
Door frames & window fixing
complete complete complete complete
8
Balcony grill fixing
complete complete complete complete
9
Roof sheet
complete
complete
complete
complete
10
Tiling
a
Toilet & Kitchen
complete
complete
complete
complete
b
Sundeck
complete
complete
complete
complete
c
Rooms
complete
complete
complete
complete
11
Solar Water heating systems
complete
complete
complete
complete
12
Painting
a
Internal
complete
complete
complete
complete
b
External
complete
complete
complete
complete




complete - completed before month of June '07
complete - in month of June '07
in progress - for month July '07


** The above table and the pictures gives the present status of various construction activities on site as on 1st July 2007. There will be no more progress updates on this website. Kindly contact Neville Fernandes, Project Manager - Villa Violeta for possession of your home. This is for the information of the homeowners.


 

East view of villas A & B

East view of villas C & D

South east view of building E

 

 

 

 

 

 

 

 

 

 

 

 

 


South view of building F

South west view of villas H & I

South east view of villas J & K

 

 

 

 

 

 

 

 

 

 

 

 


South east view of villas L & M

East view of villas N & O

North east view of villas P & Q

 

 

 

 

 

 

 

 

 

 




North view of villas R & S

North view of villas U & T

North west view of villas Z & Y

 

 

 

 


 

 

 

 

 

 

 

 




Swimming pool in front of villas
H, I & Z, Y

Swimming pool in front of villas P, Q & R, S

Violeta 1