UNDER CONSTRUCTION - Progress Report

UPDATE ON ASTER AND THE CLUB HOUSE :

This is to inform our customers in Aster that their building and the club house will not be shifted after all. The existing occupants of the private residence on the property, (for whom we had built a new, modern home close to Villa Vera) have elected not to shift at this time.

We made considerable attempts to induce them to relocate. However, we cannot wait endlessly for their decision and hence, ‘Aster’ and the club house will be located / built as per the original plan. Work has commenced on the site accordingly.

  ACTIVITY ACTIVITY STATUS
    APT A APT B APT C APT D APT E APT F APT G
1
Work in foundation & plinth
             
a
Excavation for footing
Complete
Complete
Complete
Complete
Complete
Complete
Complete
b
Concreting of footings
Complete
Complete
Complete
Complete
Complete
Complete
Complete
c
Plinth beam concreting
Complete
Complete
Complete
Complete
Complete
Complete
Complete
d
Plinth plain cement concrete(PCC)
Complete
Complete
Complete
Complete
Complete
Complete
Complete
                 
2
R.C.C work
             
a
Stilt floor columns
in progress
Complete
Complete
Complete
Complete
Complete
Complete
b
Stilt floor slab
 
Complete
Complete
Complete
Complete
Complete
Complete
c
Ground floor columns
 
Complete
Complete
Complete
Complete
Complete
Complete
d
Ground floor slab
 
Complete
Complete
Complete
Complete
Complete
Complete
e
First floor columns
 
Complete
Complete
Complete
Complete
Complete
Complete
f
First floor slab
 
Complete
Complete
Complete
Complete
Complete
Complete
g
Second floor columns
 
Complete
Complete
Complete
Complete
Complete
Complete
h
Second floor slab
 
Complete
Complete
Complete
Complete
Complete
Complete
i
Third floor columns
 
Complete
Complete
Complete
Complete
Complete
Complete
j
Third floor terrace slab
 
Complete
Complete
Complete
Complete
Complete
Complete
k Third floor roof slab  
Complete
Complete
Complete
Complete
Complete
Complete
l Staircase roof slab    
in progress
Complete
Complete
Complete
Complete
                 
3
Masonary work
             
a
Upper Ground floor 
 
Complete
Complete
Complete
Complete
Complete
Complete
b
First floor 
 
Complete
Complete
Complete
Complete
Complete
Complete
c
Second floor 
 
Complete
Complete
Complete
Complete
Complete
Complete
d Third Floor    
Complete
Complete
Complete
Complete
Complete
e
Terrace
     
Complete
Complete
Complete
Complete
                 
4 Internal plaster / Gypsum              
a
Upper Ground floor ceiling
 
Complete
Complete
Complete
Complete
Complete
Complete
b
Upper Ground floor walls
 
Complete
Complete
Complete
Complete
Complete
Complete
c
First floor ceiling
 
in progress
Complete
Complete
Complete
Complete
Complete
d First floor walls  
in progress
Complete
Complete
Complete
Complete
Complete
e Second floor walls    
in progress
Complete
Complete
Complete
Complete
f Second floor ceiling    
in progress
Complete
Complete
Complete
Complete
g Third floor ceiling      
in progress
in progress
Complete
Complete
h Third floor wall      
Complete
in progress
in progress
in progress
                 
5
External plaster
             
a
Upper Ground floor
   
in progress
Complete
Complete
Complete
Complete
b
First Floor  
   
in progress
Complete
Complete
Complete
Complete
c
Second Floor
     
Complete
Complete
Complete
Complete
d
Third Floor
     
Complete
Complete
Complete
Complete
e Terrace      
Complete
Complete
in progress
in progress
                 
6 Internal Plumbing              
a Upper Ground floor  
in progress
in progress
Complete
Complete
Complete
Complete
b First Floor      
Complete
Complete
Complete
Complete
c Second Floor      
Complete
Complete
Complete
Complete
d Third Floor      
Complete
in progress
in progress
in progress
                 
7 External Plumbing      
Complete
in progress
in progress
in progress
                 
8 Ironmongery              
a Upper Ground floor      
Complete
Complete
in progress
in progress
b First Floor      
Complete
Complete
in progress
in progress
c Second Floor      
in progress
Complete
   
d Third Floor      
in progress
in progress
   
                 
9 Wood Joinery              
a Upper Ground floor      
Complete
Complete
Complete
Complete
b First Floor      
in progress
in progress
in progress
in progress
c Second Floor      
in progress
in progress
in progress
in progress
d Third Floor              
                 
10 Tiling              
a Upper Ground floor      
in progress
in progress
   
b First Floor      
in progress
     
c Second Floor              
d Third Floor              
                 
11 Waterproofing              
a Toilet    
in progress
Complete
Complete
Complete
Complete
b Sundeck      
in progress
     
                 
12 Electrical              
a Conducting    
in progress
in progress in progress
in progress
in progress
                 
                 
complete - completed before month of Jun '08 complete - in month of Jun '08 in progress - for month of Jul '08


** ** The above table and the pictures gives the present status of various construction activities on site as on 30th June 2008. The next update will be uploaded on the website by the 2nd weekend of August. This is for the information of the homeowners.


South view of building A

North view of building B

North view of building C

East view of building D

East view of building E

South view of building F

South view of building G