VILLA VERA
UNDER CONSTRUCTION - Progress Report
UPDATE ON ASTER AND THE CLUB HOUSE :
This is to inform our customers in Aster that their building and the club house will not be shifted after all. The existing occupants of the private residence on the property, (for whom we had built a new, modern home close to Villa Vera) have elected not to shift at this time.
We made considerable attempts to induce them to relocate. However, we cannot wait endlessly for their decision and hence, ‘Aster’ and the club house will be located / built as per the original plan. Work has commenced on the site accordingly.
| ACTIVITY | ACTIVITY STATUS | |||||||
| APT A | APT B | APT C | APT D | APT E | APT F | APT G | ||
| 1 | Work in foundation & plinth |
|||||||
| a | Excavation for footing |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| b | Concreting of footings |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| c | Plinth beam concreting |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| d | Plinth plain cement concrete(PCC) |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| 2 | R.C.C work |
|||||||
| a | Stilt floor columns |
in progress |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| b | Stilt floor slab |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| c | Ground floor columns |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| d | Ground floor slab |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| e | First floor columns |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| f | First floor slab |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| g | Second floor columns |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| h | Second floor slab |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| i | Third floor columns |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| j | Third floor terrace slab |
Complete |
Complete |
Complete |
Complete |
Complete
|
Complete |
|
| k | Third floor roof slab | Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| l | Staircase roof slab | in progress |
Complete |
Complete |
Complete |
Complete |
||
| 3 | Masonary work |
|||||||
| a | Upper Ground floor |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| b | First floor |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| c | Second floor |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| d | Third Floor | Complete |
Complete
|
Complete |
Complete |
Complete |
||
| e | Terrace |
Complete |
Complete |
Complete |
Complete |
|||
| 4 | Internal plaster / Gypsum | |||||||
| a | Upper Ground floor ceiling |
Complete |
Complete |
Complete
|
Complete |
Complete |
Complete |
|
| b | Upper Ground floor walls |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| c | First floor ceiling |
in progress |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| d | First floor walls | in progress |
Complete |
Complete |
Complete |
Complete |
Complete |
|
| e | Second floor walls | in progress |
Complete |
Complete |
Complete |
Complete |
||
| f | Second floor ceiling | in progress |
Complete |
Complete |
Complete |
Complete |
||
| g | Third floor ceiling | in progress |
in progress |
Complete |
Complete |
|||
| h | Third floor wall | Complete |
in progress |
in progress |
in progress |
|||
| 5 | External plaster |
|||||||
| a | Upper Ground floor |
in progress |
Complete |
Complete |
Complete |
Complete |
||
| b | First Floor |
in progress |
Complete |
Complete |
Complete |
Complete |
||
| c | Second Floor |
Complete |
Complete |
Complete |
Complete |
|||
| d | Third Floor |
Complete |
Complete |
Complete |
Complete |
|||
| e | Terrace | Complete |
Complete |
in progress |
in progress |
|||
| 6 | Internal Plumbing | |||||||
| a | Upper Ground floor | in progress |
in progress |
Complete |
Complete |
Complete |
Complete |
|
| b | First Floor | Complete |
Complete |
Complete |
Complete |
|||
| c | Second Floor | Complete |
Complete |
Complete |
Complete |
|||
| d | Third Floor | Complete |
in progress |
in progress |
in progress |
|||
| 7 | External Plumbing | Complete |
in progress |
in progress |
in progress |
|||
| 8 | Ironmongery | |||||||
| a | Upper Ground floor | Complete |
Complete |
in progress |
in progress |
|||
| b | First Floor | Complete |
Complete |
in progress |
in progress |
|||
| c | Second Floor | in progress |
Complete |
|||||
| d | Third Floor | in progress |
in progress |
|||||
| 9 | Wood Joinery | |||||||
| a | Upper Ground floor | Complete |
Complete |
Complete |
Complete |
|||
| b | First Floor | in progress |
in progress |
in progress |
in progress |
|||
| c | Second Floor | in progress |
in progress |
in progress |
in progress |
|||
| d | Third Floor | |||||||
| 10 | Tiling | |||||||
| a | Upper Ground floor | in progress |
in progress |
|||||
| b | First Floor | in progress |
||||||
| c | Second Floor | |||||||
| d | Third Floor | |||||||
| 11 | Waterproofing | |||||||
| a | Toilet | in progress |
Complete
|
Complete |
Complete |
Complete |
||
| b | Sundeck | in progress |
||||||
| 12 | Electrical | |||||||
| a | Conducting | in progress |
in progress | in progress | in progress |
in progress |
||
| complete - completed before month of Jun '08 | complete - in month of Jun '08 | in progress - for month of Jul '08 | ||||||
** ** The above table and the pictures gives the present status of various construction activities on site as on 30th June 2008.
The next update will be uploaded on the website by the 2nd weekend of August. This is for the information of the homeowners.
![]() South view of building A |
![]() North view of building B |
![]() North view of building C |
![]() East view of building D |
![]() East view of building E |
![]() South view of building F |
![]() South view of building G |







