VILLA SERENA
UNDER CONSTRUCTION - Progress Report
ACTIVITY |
ACTIVITY STATUS |
||
| APT A | APT B | ||
| 1 | Work in foundation & plinth | ||
| a | Excavation for footing | Complete | Complete |
| b | Concreting of footings | Complete | Complete |
| c | Plinth beam concreting | Complete | Complete |
| d | Plinth Plain CementConcrete (PCC) | Complete | Complete |
| 2 | R.C.C work | ||
| a | Ground floor columns | Complete |
Complete |
| b | Ground floor slab | Complete | Complete |
| c | First floor columns | Complete | Complete |
| d | First floor slab | Complete | Complete |
| e | Second floor columns | Complete | Complete |
| f | Second floor roof slab | Complete | Complete |
| g | Third floor columns | Complete | Complete |
| h | Third floor roof slab | Complete | Complete |
| i | Staircase roof slab | Complete | Complete |
| 3 | Masonary work | ||
| a | Ground floor | Complete |
Complete |
| b | First floor | Complete |
Complete |
| c | Second floor | Complete |
Complete |
| d | Third floor | Complete |
Complete |
| 4 | Plaster | ||
| a | Internal | in progress |
in progress |
| b | External | Complete |
Complete |
| 5 | Gypsum plaster | ||
| a | Ground floor ceiling | Complete |
Complete |
| b | Ground floor walls | Complete |
in progress |
| c | First floor ceiling | Complete |
Complete |
| d | First floor walls | Complete |
Complete |
| e | Second floor walls | Complete |
Complete |
| f | Second floor ceiling | Complete |
Complete |
| g | Third floor ceiling | Complete |
Complete |
| h | Third floor walls | Complete |
Complete |
| 6 | Waterproofing | ||
| a | Toilet | in progress |
Complete |
| 7 | Electrical | ||
| a | Conduting | Complete |
Complete |
| 8 | Plumbing | Complete |
in progress |
| complete - completed before month of Jun '08 | complete - in month of Jun '08 | in progress - in month of Jul '08 | |