VILLA MARIA
UNDER CONSTRUCTION - Progress Report
Attn: Villa Maria homeowners :
As the development is complete and the homes are ready for possession this will be the final progress report. All homeowners who have not taken possession are requested to kindly contact us immediately.
VILLA MARIA |
||||||||
CONSTRUCTION PROGRESS REPORT |
||||||||
| ACTIVITY | ACTIVITY STATUS |
|||||||
| APT A | APT B | APT C | APT D | APTE | APTF | APT G | ||
| 1 | Work in foundation & plinth |
|||||||
| a | Excavation for footing |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| b | Concreting of footings |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| c | Plinth beam concreting |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| d | Plinth Plain CementConcrete(PCC) |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| 2 | R.C.C work |
|||||||
| a | Stilt floor columns |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| b | Stilt floor slab |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| c | Ground floor columns |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| d | Ground floor slab |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| e | First floor columns |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| f | First floor slab |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| g | Second floor columns |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| h | Second floor terrace slab |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| i | Second floor roof slab |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| j | Staircase roof slab |
Complete |
Complete |
Complete |
Complete |
N/A | N/A | N/A |
| k | Overhead tank |
Complete |
||||||
| 3 | Masonary work |
|||||||
| a | Ground floor |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| b | First floor |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| c | Second floor |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| d | Terrace |
Complete |
Complete |
Complete |
Complete |
Complete |
N/A | N/A |
| 4 | Plaster | |||||||
| a | Internal |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| b | External |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| 5 | Gypsum plaster |
|||||||
| a | Ground floor ceiling |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| b | Ground floor walls |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| c | First floor ceiling |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| d | First floor walls |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| e | Second floor walls |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| f | Second floor ceiling |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete
|
Complete |
| 6 | Waterproofing |
|||||||
| a | Toilet |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| b | Sundeck |
Complete
|
Complete
|
Complete |
Complete
|
Complete |
Complete |
Complete |
| 7 | Electrical |
|||||||
| a | Conduting |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| b | Wiring | Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| c | Switch Plate fixing | Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| 8 | Plumbing |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| 9 | Tiling | |||||||
| a | Flooring | Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| b | Kitchen | Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| c | Toilets | Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| 10 | Painting | |||||||
| a | Internal | in progress | in progress | in progress | in progress | in progress | in progress | in progress |
| b | External | Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| 11 | Piped Gas | |||||||
| a | Internal | Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| b | External | Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
Complete |
| 12 | Landscaping | in progress | in progress | in progress | in progress | in progress | in progress | in progress |
| complete - completed before month of March '08 | complete - in month of March '08 | in progress - for month of April '08 | ||||||
|
South view of building A |
South view of building B |
South west view of building C | West view of building D |
| South west view of building E |
North view of building F |
| North view of building G |