Homes in Goa by ACRON, Goa's leading-edge property developer
VILLA EVA
CONSTRUCTION - Progress Report

Attn: Villa Eva homeowners :

The pictures and progress report are updated as on 28th May 2008. As the development is complete and the homes are ready for possession this will be the final progress report. All homeowners who have not taken possession are requested to kindly contact us immediately.
ACTIVITY
ACTIVITY STATUS
APT A
APT B
APT C
APT D
APT E
1
Work in foundation & plinth
a
Excavation for footing
Complete
Complete
Complete
Complete
Complete
2
R.C.C work
a
Concreting of footings
Complete
Complete
Complete
Complete
Complete
b
Plinth beam concreting
Complete
Complete
Complete
Complete
Complete
c
Plinth Plain Cement Concrete(PCC)
Complete
Complete
Complete
Complete
Complete
d
Ground floor columns
Complete
Complete
Complete
Complete
Complete
e
Ground floor slab
Complete
Complete
Complete
Complete
Complete
f
Firsr floor columns
Complete
Complete
Complete
Complete
Complete
g
Firsr floor slab
Complete
Complete
Complete
Complete
Complete
h
Second floor columns
Complete
Complete
Complete
Complete
Complete
i
Second floor terrace slab
Complete
Complete
Complete
Complete
Complete
j
Second floor roof slab
Complete
Complete
Complete
Complete
Complete
k
Staircase roof slab
Complete
Complete
Complete
Complete
Complete
3
Masonary work
a
Ground floor masonary
Complete
Complete
Complete
Complete
Complete
b
First floor  masonary
Complete
Complete
Complete
Complete
Complete
c
Second floor  masonary
Complete
Complete
Complete
Complete
Complete
4
Internal plaster / Gypsum
a
Ground floor
Complete
Complete
Complete
Complete
Complete
b
First floor 
Complete
Complete
Complete
Complete
Complete
c
Secondfloor
Complete
Complete
Complete
Complete
Complete
5
External plaster
a
Ground floor
Complete
Complete
Complete
Complete
Complete
b
First floor  
Complete
Complete
Complete
Complete
Complete
c
Second floor
Complete
Complete
Complete
Complete
Complete
6
Internal Plumbing
a
Ground floor
Complete
Complete
Complete
Complete
Complete
b
First floor
Complete
Complete
Complete
Complete
Complete
c
Second floor
Complete
Complete
Complete
Complete
Complete
7
External Plumbing
Complete
Complete
Complete
Complete
Complete
8
Ironmongery
a
Ground floor
Complete
Complete
Complete
Complete
Complete
b
First floor
Complete
Complete
Complete
Complete
Complete
c
Second floor
Complete
Complete
Complete
Complete
Complete
9
Joinery
a
Ground floor
Complete
Complete
Complete
Complete
b
First floor
Complete
Complete
Complete
Complete
Complete
c
Second floor
Complete
Complete
Complete
Complete
Complete
10
Tiling
a
Kitchen
Complete
Complete
Complete
Complete
Complete
b
Toilet
Complete
Complete
Complete
Complete
Complete
c
Rooms
Complete
Complete
Complete
Complete
Complete
d
Sundeck
Complete
Complete
Complete
Complete
Complete
e
Staircase
Complete
Complete
Complete
Complete
Complete
11
Land Development
Complete
Complete
Complete
Complete
Complete
12
Roofing
Complete
Complete
Complete
Complete
Complete
13
LPG Pipe line-external
Complete
Complete
Complete
Complete
Complete
14
LPG Pipe line-internal
Complete
Complete
Complete
Complete
Complete
APT F
APT F
APT F
VILLAS K,L
VILLAS M,N
1
Work in foundation & plinth
a
Excavation for footing
Complete
Complete
Complete
Complete
Complete
2
R.C.C work
a
Concreting of footings
Complete
Complete
Complete
Complete
Complete
b
Plinth beam concreting
Complete
Complete
Complete
Complete
Complete
c
Plinth Plain Cement Concrete(PCC)
Complete
Complete
Complete
Complete
Complete
d
Ground floor columns
Complete
Complete
Complete
Complete
Complete
e
Ground floor slab
Complete
Complete
Complete
Complete
Complete
f
First floor columns
Complete
Complete
Complete
Complete
Complete
g
First floor slab
Complete
Complete
Complete
N/A
N/A
h
Second floor columns
Complete
Complete
Complete
N/A
N/A
i
Second floor terrace slab
Complete
Complete
Complete
N/A
N/A
j
Second floor roof slab
Complete
Complete
Complete
Complete
Complete
3
Masonary work
a
Ground floor  masonary
Complete
Complete
N/A
Complete
Complete
b
First floor masonary
Complete
Complete
Complete
Complete
Complete
c
Second floor masonary 
Complete
Complete
N/A
N/A
4
Internal Plaster /Gypsum
a
Stilt Floor
N/A
Complete
N/A
N/A
b
Ground Floor
Complete
Complete
Complete
Complete
Complete
c
First Floor
Complete
Complete
Complete
Complete
Complete
d
Second Floor
Complete
Complete
Complete
N/A
N/A
5
External Plaster
a
Ground floor 
Complete
Complete
Complete
Complete
Complete
b
First floor
Complete
Complete
Complete
Complete
Complete
c
Second floor
Complete
Complete
Complete
N/A
N/A
6
Internal plumbing
a
Ground floor
Complete
Complete
Complete
Complete
Complete
b
First floor
Complete
Complete
Complete
Complete
Complete
c
Second floor
Complete
Complete
Complete
N/A
N/A
7
External Vertical Plumbing
Complete
Complete
CompleteComplete Complete
8
Ironmongery
a
Ground floor
Complete
Complete
Complete
Complete
Complete
b
First floor
Complete
Complete
Complete
Complete
Complete
c
Second floor
Complete
Complete
Complete
N/A
N/A
9
Joinery
a
Ground floor
Complete
Complete
Complete
Complete
Complete
b
First floor
Complete
Complete
Complete
Complete
Complete
c
Second floor
Complete
Complete
Complete
N/A
N/A
10
Tiling
a
Kitchen
Complete
Complete
Complete
Complete
Complete
b
Toilet
Complete
Complete
Complete
Complete
Complete
c
Rooms
Complete
Complete
Complete
Complete
Complete
d
Sundeck
Complete
Complete
in progress
Complete
Complete
e
Staircase
Complete
Complete
in progress
Complete
Complete
11
Land development
Complete
Complete
Complete
Complete
Complete
12
Roofing
Complete
Complete
Complete
Complete
Complete
13
LPG Pipe line - external
Complete
Complete
Complete
Complete
Complete
14
LPG Pipe line -external
Complete
Complete
Complete
Complete
Complete
15
Int. Road
16
Int. Painting
in progress
in progress
in progress
Complete
Complete
17
Ext. Painting
Complete
Complete
in progress
Complete
Complete
18
Tank Block 'O'
in progress
19
Tennis court
Complete
complete - completed before month of May '08
complete - in month of May '08
in progress - for month of June '08






 


Building E, with pool and landscaping

Building H

 

 

 

 

 


landscaping in front of D and E

landscaping work between
buildings B and C

North East view of building H

North west view of villas K & L.

Security room with well

South East view of building E

Tennis court and club house

West view of pool 2 with landscaping