Homes in Goa by ACRON, Goa's leading-edge property developer

VICENTE GREENS
UNDER CONSTRUCTION - Progress Report

  ACTIVITY ACTIVITY STATUS
    APT A APT B APT C APT D APT E
1
Work in foundation & plinth
         
a
Excavation for footing
Complete
Complete
Complete
b
Concreting of footings
Complete
Complete
in progress
c
Foundation masonry
Complete
in progress
in progress
d
Plinth beam concreting
Complete
in progress
in progress
e
Backfilling in plinth
in progress
in progress
in progress
f
Plinth plain cement concrete(PCC)
in progress
in progress
             
2
R.C.C work
         
a
Stilt floor columns
-
-
in progress
b
Stilt floor slab
-
-
in progress
c
Upper Ground floor columns
in progress
in progress
d
Upper Ground floor slab
in progress
in progress
e
First floor columns
in progress
f
First floor slab
in progress
g
Second floor columns
h
Second floor slab
i
Third floor columns
j
Third floor terrace slab
k Third floor roof slab
l Staircase column
m Staircase roof slab
             
3
Masonary work
         
a
Upper Ground floor 
b
First floor 
c
Second floor 
d Third Floor
e
Terrace
             
4 Internal plaster / Gypsum          
a
Upper Ground floor ceiling
b
Upper Ground floor walls
c
First floor ceiling
d First floor walls
e Second floor walls
f Second floor ceiling
g Third floor ceiling
h Third floor wall
             
5
External plaster
         
a
Upper Ground floor
b
First Floor  
c
Second Floor
d
Third Floor
e Terrace
             
6 Internal Plumbing          
a Upper Ground floor
b First Floor
c Second Floor
d Third Floor
             
7 External Plumbing
             
8 Ironmongery          
a Upper Ground floor
b First Floor
c Second Floor
d Third Floor
             
9 Wood Joinery          
a Upper Ground floor
b First Floor
c Second Floor
d Third Floor
             
10 Tiling          
a Upper Ground floor
b First Floor
c Second Floor
d Third Floor
e Silt Parking - LGF
f Staircase
             
11 Waterproofing          
a Toilet
             
12 Electrical          
a Conducting & Box Fixing
             
13 Internal Painting          
a Upper Ground floor
b First Floor
c Second Floor
d Third Floor
             
14 External Painting
             
15 Solar Heating Systems
             
16 Galvalume Roofing
             
17 Lift
             
complete - completed before month of  May 2010 complete - in month of June 2010 in progress - for month of June 2010


Building A

Building A

Building B

Building C